Lead Time Chart

Curb Adapters: 5 days


Welded Curbs and Standard Welded Product: 10-12 days


Vibration Isolation Curbs: 10 days standard isolation; 15-18 days calculated


Knocked Down Curbs: 10 days


Power Exhaust, Economizers: 12-15 days


Mixing Boxes: 15 days


Most all other Non-Welded product: 10 days


Lead times are for 2-12.5 ton units.



Contact ProVent for large items and large quantities for accurate lead times.



Lead times are current as of 10/16/2020